A double shot molding payment plan should be connected to verifiable tooling results instead of relying only on scheduled dates. A practical 50%-30%-20% T/T structure can be used: pay 50% when the mold order is confirmed, release 30% after T1 samples meet the agreed alignment, dimensional, surface, and stability requirements, and pay the remaining 20% before shipment once final inspection and sample approval are complete.
The initial 50% payment authorizes mold development and production after the technical requirements have been approved. The second 30% should not be triggered simply by reaching a calendar date. It should follow a documented T1 review in which the buyer evaluates the trial parts against the approved drawing, reference sample, and agreed quality requirements.
The final 20% payment is released before shipment after the tooling, samples, and correction status have passed the agreed final checks. This arrangement gives both parties a clear record of what has been completed and makes payment decisions easier to manage when a trial requires additional modification.
For the custom plastic injection mold product, the listed steel materials include P20, 718H, and 1.2738. The mold is compatible with materials such as ABS, PC, and PP, and the stated precision tolerance is ±0.02 mm. Available configurations include single-cavity and multi-cavity tooling, with polishing, textured, or matte surface finishes. The listed mold service life ranges from 50,000 to 800,000 shots. These specifications should be checked against the approved engineering documents and the actual T1 sample inspection results.

For every trial, the acceptance record should identify the mold version, cavity arrangement, sample status, inspection findings, and any correction required. Double shot tooling also needs a specific review of how accurately the two molded sections meet, whether the materials bond or fit as intended, and whether the samples remain stable across the agreed number of cycles.

Longterm has supplied a double shot overmolding mold to a French product brand for a consumer electronics shell. The recorded customer feedback noted satisfactory alignment, stable trial samples, and a professional, responsive service experience. This kind of documented result can be attached to the T1 acceptance record and used as evidence for the intermediate payment.
| Milestone | Payment condition | Required evidence |
|---|---|---|
| Mold order confirmation | 50% payment to begin the project | Approved specifications, material selection, cavity plan, drawings, and sample references |
| T1 trial and sample review | 30% payment after acceptance of T1 results | Alignment review, dimensional inspection, surface assessment, mold trial results, and sample confirmation |
| Final pre-shipment approval | 20% payment before shipment | Completed full inspection, trial documentation, sample approval, and confirmed correction status |
| Complex double shot or overmold validation | Release based on acceptance rather than elapsed time | Multi-cycle performance, stable samples, section alignment, and agreed quality records |
What evidence should support the 30% T1 payment?
The payment should follow a written T1 sample review. The record should show the mold trial outcome, section alignment, measured dimensions, surface condition, sample approval status, and any deviations from the approved requirements.
Which double shot molding results can be measured?
Useful measurements include the alignment between molded sections, dimensional inspection results, surface inspection findings, sample stability, and observations from repeated mold cycles. The stated ±0.02 mm tolerance can also be compared with the approved drawing when it applies to the selected mold design.
How should corrections affect payment?
If the samples need correction, the acceptance record should list the open items and identify which payment gate remains pending. Longterm lists mold modification, maintenance, online technical guidance, and spare parts support among its after-sales services, allowing the correction process to be tracked separately from the payment schedule.
Use the 50%-30%-20% structure as a results-based payment framework. The first payment launches the tooling work, the second follows verified T1 performance, and the final payment depends on complete inspection and confirmed samples before shipment. For double shot projects, retain records for alignment, dimensional accuracy, surface quality, trial stability, and multi-cycle performance.
Longterm provides OEM custom plastic injection molds, double shot molds, overmolding services, and mold development combined with plastic injection mass production. The company holds ISO 9001:2015 certification covering the design, manufacturing, and sales of precision molds and the sales of plastic products. For technical solutions or project support, contact Roger Luo at rogerluo@longterm-mold.com.
Longterm Manufacturing Solutions Limited was established in 2010 and serves international customers with mold design, tooling, precision machining, mold manufacturing, and plastic parts production. The company has 50 employees, including 5 R&D engineers focused on molds and precision machining. Its capabilities cover injection mold structural design, precision CNC component development, sample verification, and manufacturing process optimization. Longterm supports customers across several industries and operates with ISO 9001:2015 certification.