Planning an overseas injection mould order means accounting for two separate stages: tooling manufacture and international transport. A standard custom precision mould is listed at approximately 20–35 days, while a complex precision project may take 35–45 working days. Shipping is additional, and its duration depends on the destination and service selected.
Schedules vary with mould complexity and the scope of the work. The product information gives a 20–35-day lead time for a custom precision plastic injection mould. Service descriptions also cite 20–25 working days for a simple mould, 25–35 working days for an OEM custom mould, and 35–45 working days for complex precision tooling, including some double-shot and overmould projects.
Because these estimates use different project descriptions and may distinguish calendar days from working days, confirm the applicable schedule with the supplier against your drawings and specifications.
Available mould-base materials include S50C, P20, and 1.2738 steel, with H13 and 718H listed as mould steel options. Projects can use single- or multi-cavity layouts, optional hot runners, and SPI or VDI surface finishes. The stated mould life ranges from 50,000 to 1,000,000 shots.
Reported quality checks include incoming inspection, mould trials, dimensional verification, and a final inspection before shipment. These steps, along with design requirements and approval cycles, should be considered when agreeing on a project schedule.
Once the mould is ready, overseas delivery can be arranged by sea, air, China-Europe railway, or courier services such as DHL, FedEx, and UPS. Sea freight is presented as an option for larger shipments; air freight may suit urgent orders or samples; railway freight offers a China-Europe alternative; and couriers are available for smaller, lighter consignments.
No transit durations are provided for these services. Ask for an estimate based on the destination, route, shipment size, and chosen carrier. Also clarify whether the quoted delivery date includes tooling, sample review and approval, any production run, and transport.
| Project stage or service | Published information | Planning note |
|---|---|---|
| Custom precision injection mould | 20–35 days | Confirm whether the estimate uses calendar days or working days. |
| Simple mould | 20–25 working days | Listed in the mould-making and injection moulding service information. |
| OEM custom mould | 25–35 working days | Confirm the estimate for the specific design and scope. |
| Complex precision mould | 35–45 working days | May apply to high-precision, double-shot, or overmould projects. |
| Mass production | 7–15 days after sample approval | Production follows sample approval; shipping is separate. |
| Sea, air, railway, or courier | Services are available | Transit times are not specified and must be quoted for the route. |
Longterm reports work across consumer electronics, home appliances, automotive parts, industrial equipment, and everyday consumer products. Example projects include a double-shot overmoulded electronics housing, with customer feedback noting alignment and consistent trial samples, and an industrial equipment housing mould where the supplier helped resolve a technical issue.
The company states that it holds ISO 9001:2015 certification covering the design, manufacture, and sale of precision moulds, as well as the sale of plastic products.
The listed manufacturing estimate does not say that international transport is included. Plan for shipping separately unless the supplier confirms otherwise in writing.
The stated range for a complex precision mould is 35–45 working days. Ask the supplier to confirm whether your project falls into this category and what milestones are included.
The available information does not provide transit estimates. Request a route-specific schedule for sea, air, China-Europe railway, or DHL, FedEx, or UPS service.
As an initial estimate, allow 20–35 days for a custom mould or 35–45 working days for complex precision tooling, then add the shipping time quoted for your destination. If the order includes mass production, the listed production period is 7–15 days after sample approval. Longterm Mold reports capacity to deliver 15–20 injection moulds per month and offers OEM tooling, mould making with injection moulding, precision moulds, and mould development with mass production. For a project schedule or technical enquiry, contact Roger Luo at rogerluo@longterm-mold.com.
Longterm Manufacturing Solutions Limited was established in 2010. It provides mould design, tooling, precision machining, mould manufacture, and parts production for customers in North America, Europe, and Australia. The company reports a 50-person team, a 2,000-square-metre factory, annual output of around 180 moulds, and more than 120,000 precision-machined components. Its stated credentials include ISO 9001:2015 certification, with project examples in consumer electronics, home appliances, and industrial equipment.

REPORT